Qt Creator Releases: Difference between revisions

From Qt Wiki
Jump to navigation Jump to search
(fix week numbers to follow ISO 8601)
(Preliminary plan for 2024)
 
(86 intermediate revisions by 3 users not shown)
Line 1: Line 1:
[[Category:Tools::QtCreator]]
[[Category:Tools::QtCreator]]


===Qt Creator Release Cycle===
===Upcoming Releases===
 
Tentative dates:
 
Qt Creator 11.0.3: ~Sep 28 2023
 
Qt Creator 12
 
* Feature freeze wk39 (~Sep 28 2023)
* Beta release wk41 (~Oct 12 2023)
* String freeze wk43 (~Oct 26 2023)
* RC release wk45 (~Nov 9 2023)
* Final release wk47 (~Nov 23 2023)


We aim for 3 Qt Creator minor releases each year. Each minor release goes through the following stages before the final release date:
Qt Creator 13


* T-8 Weeks: Feature freeze
* Feature freeze wk5 (~Feb 1 2024)
* T-6 Weeks: Beta release + soft string freeze
* Beta release wk7 (~Feb 15 2024)
* T-4 Weeks: String freeze
* String freeze wk9 (~Feb 29 2024)
* T-2 Weeks: Release candidate
* RC release wk11 (~Mar 14 2024)
* T-0 Weeks: Final release
* Final release wk13 (~Mar 28 2024)


These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.
Qt Creator 14


Patch releases can happen after the final release, mostly with the scope of fixing brown paper bag and high priority issues (see also the [[Submit-Policies|Qt Creator Submit Policies]] ''[qt.io]''). We do not maintain multiple Qt Creator minor releases in parallel, usually there is no patch release after the beta of the next minor release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.
* Feature freeze wk22 (~May 30 2024)
* Beta release wk24 (~Jun 13 2024)
* String freeze wk26 (~Jun 27 26 2024)
* RC release wk28 (~Jul 11 2024)
* Final release wk30 (~Jul 25 2024)


The schedule for the next minor is typically set around release time, starting with a period about two months which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)
Qt Creator 15


===Upcoming Releases===
* Feature freeze wk40 (~Oct 3 2024)
* Beta release wk42 (~Oct 17 2024)
* String freeze wk44 (~Oct 31 2024)
* RC release wk46 (~Nov 14 2024)
* Final release wk48 (~Nov 28 2024)


Tentative dates:
The mentioned dates are typically Thursdays of the weeks, packages are meant to be ready by Tuesday. Actual release then typically happens on Wednesday or Thursday.


Qt Creator 4.3.1: With Qt 5.9.1 (wk26?)
A collection of older release plans is found at [[Old Qt Creator Releases]].


Qt Creator 4.4
===Qt Creator Release Cycle===


* Feature freeze wk27 (~ Jul 4 2017)
We aim for 3 Qt Creator major releases each year. Each release goes through the following stages before the final release date:
* Beta release wk29 (~ Jul 18 2017)
* String freeze wk31 (~ Aug 1 2017)
* Release candidate wk33 (~ Aug 15 2017)
* Final release wk35 (~ Aug 29 2017)


Qt Creator 4.5
* T-8 Weeks: Feature freeze
* T-6 Weeks: Beta release + soft string freeze
* T-4 Weeks: String freeze
* T-2 Weeks: Release candidate
* T-0 Weeks: Final release


* Feature freeze wk41 (~ Oct 10 2017)
These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.
* Beta release wk43 (~ Oct 24 2017)
* String freeze wk45 (~ Nov 7 2017)
* Release candidate wk47 (~ Nov 21 2017)
* Final release wk49 (~ Dec 5 2017)


The mentioned dates are typically Tuesdays of the weeks, packages are meant to be ready by then. Actual release typically happens on Wednesday or Thursday.
Patch releases can happen after the final major release, mostly with the scope of fixing embarrassing bugs and high priority issues (see also the [[Submit-Policies|Qt Creator Submit Policies]] ''[qt.io]''). We do not maintain multiple Qt Creator major releases in parallel, usually there is no patch release after the beta of the next release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.


A collection of older release plans is found at [[Old Qt Creator Releases]].
The time after a final (.0) release starts with a period of about two months (52 weeks / 3 releases - 8 weeks from feature freeze to final = 9 1/3 weeks) which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)

Latest revision as of 08:41, 22 September 2023


Upcoming Releases

Tentative dates:

Qt Creator 11.0.3: ~Sep 28 2023

Qt Creator 12

  • Feature freeze wk39 (~Sep 28 2023)
  • Beta release wk41 (~Oct 12 2023)
  • String freeze wk43 (~Oct 26 2023)
  • RC release wk45 (~Nov 9 2023)
  • Final release wk47 (~Nov 23 2023)

Qt Creator 13

  • Feature freeze wk5 (~Feb 1 2024)
  • Beta release wk7 (~Feb 15 2024)
  • String freeze wk9 (~Feb 29 2024)
  • RC release wk11 (~Mar 14 2024)
  • Final release wk13 (~Mar 28 2024)

Qt Creator 14

  • Feature freeze wk22 (~May 30 2024)
  • Beta release wk24 (~Jun 13 2024)
  • String freeze wk26 (~Jun 27 26 2024)
  • RC release wk28 (~Jul 11 2024)
  • Final release wk30 (~Jul 25 2024)

Qt Creator 15

  • Feature freeze wk40 (~Oct 3 2024)
  • Beta release wk42 (~Oct 17 2024)
  • String freeze wk44 (~Oct 31 2024)
  • RC release wk46 (~Nov 14 2024)
  • Final release wk48 (~Nov 28 2024)

The mentioned dates are typically Thursdays of the weeks, packages are meant to be ready by Tuesday. Actual release then typically happens on Wednesday or Thursday.

A collection of older release plans is found at Old Qt Creator Releases.

Qt Creator Release Cycle

We aim for 3 Qt Creator major releases each year. Each release goes through the following stages before the final release date:

  • T-8 Weeks: Feature freeze
  • T-6 Weeks: Beta release + soft string freeze
  • T-4 Weeks: String freeze
  • T-2 Weeks: Release candidate
  • T-0 Weeks: Final release

These times are approximate and can vary a bit, depending on the state of Qt Creator during the process.

Patch releases can happen after the final major release, mostly with the scope of fixing embarrassing bugs and high priority issues (see also the Qt Creator Submit Policies [qt.io]). We do not maintain multiple Qt Creator major releases in parallel, usually there is no patch release after the beta of the next release has been released. Qt Creator’s schedule is not aligned with Qt’s schedule, but we typically provide a patch release exactly matching Qt releases which is then released at the same time.

The time after a final (.0) release starts with a period of about two months (52 weeks / 3 releases - 8 weeks from feature freeze to final = 9 1/3 weeks) which focuses on feature development for the upcoming release. (During that time there might be patch releases as described above.)